God wants me to be a person who have strength, rather than a good-looking doll. When I chose the IT industry I have proven to God my strength. But God forced me to keep moving. Oracle 1Z0-535 exam is a major challenge in my life, so I am desperately trying to learn. But it does not matter, because I purchased ITCertKing's Oracle 1Z0-535 exam training materials. With it, I can pass the Oracle 1Z0-535 exam easily. Road is under our feet, only you can decide its direction. To choose ITCertKing's Oracle 1Z0-535 exam training materials, and it is equivalent to have a better future.

Are you worried about how to passs the terrible Oracle 1Z0-535 exam? Do not worry, With ITCertKing's Oracle 1Z0-535 exam training materials in hand, any IT certification exam will become very easy. ITCertKing's Oracle 1Z0-535 exam training materials is a pioneer in the Oracle 1Z0-535 exam certification preparation.

Exam Code: 1Z0-535
Exam Name: Oracle (Primavera P6 Enterprise Project Portfolio Management Essentials)
One year free update, No help, Full refund!
Total Q&A: 70 Questions and Answers
Last Update: 2013-10-22

Now in such society with a galaxy of talents, stabilizing your job position is the best survival method. But stabilizing job position is not so easy. When others are fighting to improve their vocational ability, if you still making no progress and take things as they are, then you will be eliminated. In order to stabilize your job position, you need to constantly improve your professional ability and keep up with the pace of others to let you not fall far behind others.

ITCertKing Oracle 1Z0-535 exam training materials can help you to come true your dreams. Because it contains all the questions of Oracle 1Z0-535 examination. With ITCertKing, you could throw yourself into the exam preparation completely. With high quality training materials by ITCertKing provided, you will certainly pass the exam. ITCertKing can give you a brighter future.

Now in this time so precious society, I suggest you to choose ITCertKing which will provide you with a short-term effective training, and then you can spend a small amount of time and money to pass your first time attend Oracle certification 1Z0-535 exam.

Now many IT professionals agree that Oracle certification 1Z0-535 exam certificate is a stepping stone to the peak of the IT industry. Oracle certification 1Z0-535 exam is an exam concerned by lots of IT professionals.

1Z0-535 Free Demo Download: http://www.itcertking.com/1Z0-535_exam.html

NO.1 0You are a Portfolio Manager who opened a specific portfolio. You refreshed the filter. However, some
of the projects that were previously in the portfolio are no longer there. What happened?
A. You no longer have sufficient Project level security to view the "missing" projects' data.
B. Your Web license was revoked to allow other users to interface with the project
C. The value of the code assigned to the missing projects had changed.
D. The projects were deleted when the Miter was refreshed.
Answer: A

Oracle test   1Z0-535   1Z0-535 exam prep   1Z0-535 exam prep

NO.2 You are a Project Manager whose projects are integrated with Financial Management System (FMS).
The FMS pushes Actual Costs and Actual Hours to your projects as of the Actual Date. Updating
Percent complete using the pushed Actual Dates, Actual Costs, and Actual Hours has created inaccurate
pictures of the overall % complete, because there are steps within activities that clearly have not
completed. Which Percent Complete Type would be the best selection for activities in this project?
A. Physical
B. Units
C. Effort
D. Duration
Answer: A

Oracle study guide   1Z0-535 test   1Z0-535 certification training   1Z0-535 pdf

NO.3 An activity has an Original Duration of 10, and a Remaining Duration of 10. The Actual Start is assigned
to the activity.
Physical % is updated to equal 80%.
What is the Remaining Duration for this activity.?
A. 80
B. 10
C. 2
D. 8
Answer: B

Oracle   1Z0-535   1Z0-535 pdf   1Z0-535 original questions

NO.4 The Project Manager selects the ° U pda t e un it s w hen cos t s change on r esou r ce ass i gn m en t ¡± o p t i o n o
Calculations tab in Project Details.
The Budgeted Cost is $2,000 and the Budgeted Units is 80 for the resource on an activity. If the User
assigns the activity an Actual Cost of $1,000, what is the Actual Units for the resource?
A. 70
B. 40
C. 60
D. 80
Answer: B

Oracle   1Z0-535 dumps   1Z0-535 exam simulations   1Z0-535 exam

NO.5 Cost Variance is calculated as______.
A. Earned Value Cost - Actual Cost
B. the Actual Cost of Work Performed
C. the Budgeted Cost of Work Scheduled
D. Budget at Completion - Earned Value Cost
Answer: A

Oracle   1Z0-535 exam prep   1Z0-535

NO.6 What takes the highest precedence during Resource Leveling?
A. Leveling priority
B. Mandatory constraint
C. Topological sequent
D. Resource Calendar
Answer: B

Oracle study guide   1Z0-535   1Z0-535   1Z0-535

NO.7 You are a Portfolio Manager looking for a new portfolio that you manually created for your have clicked
the Group By drop-down list in Portfolios.
Which option should you select to quickly find your portfolio?
A. Global Portfolio
B. Global Filtered Portfolio
C. User Portfolio
D. User Filtered Portfolio
Answer: D

Oracle   1Z0-535   1Z0-535   1Z0-535 test answers

NO.8 Where are "User Defined Fields" typically maintained?
A. in the Web interface, in the preferences section
B. in the Client interface by the system administrator
C. in the Web interface, on the Activities tab
D. in the Client interface under Admin Preferences
Answer: D

Oracle   1Z0-535   1Z0-535 answers real questions

NO.9 Select the true statement regarding Global Preferences in Primavera P6 EPPM Web Interface.
A. Global Preferences are shared among all users.
B. Global Preferences are customized at the user level.
C. Global Preferences are controlled by the System Administrator
D. Global Preferences are controlled by Global Security Profiles.
Answer: D

Oracle   1Z0-535   1Z0-535 answers real questions   1Z0-535 original questions   1Z0-535 test questions

NO.10 Select the true statement regarding Portfolio Scenarios.
A. You can add user access to the Portfolio Scenario from waterline analysis.
B. You can save the Waterline Analysis as a new scenario.
C. You can update individual project status from the Waterline Analysis/Scenario.
D. You can create a new portfolio from the Waterline Analysis.
Answer: D

Oracle   1Z0-535 answers real questions   1Z0-535

ITCertKing offer the latest MSC-431 exam material and high-quality 000-123 pdf questions & answers. Our HP2-B103 VCE testing engine and 1Z0-060 study guide can help you pass the real exam. High-quality HP2-B104 dumps training materials can 100% guarantee you pass the exam faster and easier. Pass the exam to obtain certification is so simple.

Article Link: http://www.itcertking.com/1Z0-535_exam.html

没有评论:

发表评论