Best Microsoft 70-178 test training guide

The ITCertKing Free Microsoft 70-178 sample questions, allow you to enjoy the process of buying risk-free. This is a version of the exercises, so you can see the quality of the questions, and the value before you decide to buy. We are confident that ITCertKing the Microsoft 70-178 sample enough you satisfied with the product. In order to ensure your rights and interests,ITCertKing commitment examination by refund. Our aim is not just to make you pass the exam, we also hope you can become a true IT Certified Professional. Help you get consistent with your level of technology and technical posts, and you can relaxed into the IT white-collar workers to get high salary.

ITCertKing's Microsoft 70-178 exam training materials' simulation is particularly high. You can encounter the same questions in the real real exam. This only shows that the ability of our IT elite team is really high. Now many ambitious IT staff to make their own configuration files compatible with the market demand, to realize their ideals through these hot IT exam certification. Achieved excellent results in the Microsoft 70-178 exam. With the Microsoft 70-178 exam training of ITCertKing, the door of the dream will open for you.

Whatever exam you choose to take, ITCertKing training dumps will be very helpful to you. Because all questions in the actual test are included in ITCertKing practice test dumps which provide you with the adequate explanation that let you understand these questions well. As long as you master these questions and answers, you will sail through the exam you want to attend.

Exam Code: 70-178
Exam Name: Microsoft (Microsoft Project 2010, Managing Projects)
One year free update, No help, Full refund!
Total Q&A: 70 Questions and Answers
Last Update: 2014-01-03

Everyone has a utopian dream in own heart. Dreams of imaginary make people feel disheartened. In fact, as long as you take the right approach, everything is possible. You can pass the Microsoft 70-178 exam easily. Why? Because you have ITCertKing's Microsoft 70-178 exam training materials. ITCertKing's Microsoft 70-178 exam training materials are the best training materials for IT certification. It is famous for the most comprehensive and updated by the highest rate. It also can save time and effort. With it, you will pass the exam easily. If you pass the exam, you will have the self-confidence, with the confidence you will succeed.

In this era, everything is on the rise. Do not you want to break you own? Double your salary, which is not impossible. Through the Microsoft 70-178 exam, you will get what you want. ITCertKing will provide you with the best training materials, and make you pass the exam and get the certification. It's a marvel that the pass rate can achieve 100%. This is indeed true, no doubt, do not consider, act now.

70-178 Free Demo Download: http://www.itcertking.com/70-178_exam.html

NO.1 You need to set the default constraint type for all new tasks to As Late As Possible. What should you
do?
A. Select all tasks, and then click Layout.
B. In the Options dialog box, enable the New Tasks are effort driven check box.
C. Select all tasks, and then set the constraint type to As Late As Possible.
D. In the Project Information window, from the Schedule From drop-down list box, select Project Finish
Date.
Answer: D

Microsoft study guide   70-178 original questions   70-178 exam simulations   70-178 certification

NO.2 You have a Project 2010 schedule that contains the following tasks:
Inactive tasks
Manually scheduled tasks
Manually scheduled summary tasks
Tasks that contain strikethrough font
You want to save the schedule as a Project 2007 project. You need to ensure that no new milestones are
created. What should you do.?
A. Change all inactive tasks to active tasks.
B. Change all tasks that contain strikethrough font to tasks that include normal font.
C. Change all manually scheduled summary tasks to automatic scheduling.
D. Change all manually scheduled tasks to automatic scheduling.
Answer: C

Microsoft exam dumps   70-178 questions   70-178   70-178   70-178 braindump

NO.3 You manage a project according to the schedule as shown in the exhibit.
You need to set the Task Mode for task 4 to be the same as task 6. What should you do?
A. Create a task dependency from Task 4 to Task 6.
B. Set Task 4 as critical.
C. Add a 1 day lead to Task 4.
D. Set Task 4 as manually scheduled.
Answer: D

Microsoft answers real questions   70-178   70-178   70-178

NO.4 You use bottom-up scheduling. You need to group four consecutive tasks in a major phase. You
highlight the four tasks. Which command should you use?
A. Outdent
B. Fill Down
C. Insert Summary
D. Move Task
Answer: C

Microsoft braindump   70-178 certification   70-178   70-178   70-178 test answers

NO.5 You manage several projects. Each project has shared resources and work distribution. You need to
ensure that you can adjust the workload for specific resources used across multiple project schedules.
What should you do?
A. Enable the Load Summary Resource Assignments option. Then, select the Level Resource function on
each project.
B. Open the individual schedules and use the Visual Reports option. Then, use the Resource Usage view
to manually modify resource Work.
C. Open a blank project and select Insert Subproject for each project schedule. Then, use the Level
Resource function for selected resources.
D. Open the shared Resource Pool for each project schedule. Then, use the Level Resources function.
Answer: C

Microsoft   70-178 demo   70-178   70-178   70-178   70-178 certification

NO.6 A section of your project contains only a summary task along with four subtasks and a milestone. You
discover that the section is located in the incorrect phase and has the incorrect Work Breakdown
Structure (WBS) numbering. You need to move the section to another phase of the project. You also need
to ensure that the section reflects the correct WBS numbering. What should you do?
A. Select the summary task and change the scheduling mode to Manually Scheduled.
B. Select the entire section and click Move Task.
C. Drag the summary task.
D. Modify the start and finish dates of the summary task.
Answer: C

Microsoft braindump   70-178 test   70-178   70-178 answers real questions   70-178

NO.7 You manage a project that specifies all constraint types to As Soon As Possible. You discover that one
of your key tasks is scheduled to end prior to the targeted finish date. You need to display the targeted
finish date on the default Gantt chart. What should you modify in the Task Information window?
A. Set the Deadline date field.
B. Set the Constraint date field.
C. Set the Finish date field.
D. Select the Mark task as milestone check box.
E. Select the Display on Timeline check box.
Answer: A

Microsoft test   70-178   70-178 test answers   70-178

NO.8 The first major phase of your project is scheduled for a duration of 45 days. However, you do not have
task information for other phases. You need to indicate that the duration of the entire project is 200 days.
What should you do?
A. Select the Project Summary Task option.
B. Select the Summary Tasks option.
C. Create a manually scheduled summary task.
D. Update the project calendar.
Answer: C

Microsoft   70-178   70-178   70-178

NO.9 You need to view Task ID 0 on your project plan. What should you do?
A. On the Advanced tab of the Project 2010 options, select Show Status Bar.
B. On the Format tab, select Summary Tasks.
C. On the Format tab, select Project Summary Task.
D. Insert a new Summary Task.
Answer: C

Microsoft   70-178   70-178   70-178   70-178

NO.10 The project you manage has only part-time resources. The part-time resources work four hours a day
from Wednesday through Saturday. You need to create a new calendar and set the calendar as the
default for your project. Which two actions should you perform? Each correct answer presents part of the
solution.
A. Select the part-time calendar from the Change Working Time window.
B. Set the calendar type to part-time for all tasks.
C. Select the part-time calendar from the Project Information window.
D. On the Project tab, Select Change Working Time, and then click Create New Calendar.
E. Change the Calendar type in the Project Options dialog box.
Answer: CD

Microsoft   70-178 exam prep   70-178   70-178

ITCertKing offer the latest 70-332 exam material and high-quality 1Z0-060 pdf questions & answers. Our 000-959 VCE testing engine and ACMA_6.1 study guide can help you pass the real exam. High-quality 70-341 dumps training materials can 100% guarantee you pass the exam faster and easier. Pass the exam to obtain certification is so simple.

Article Link: http://www.itcertking.com/70-178_exam.html

没有评论:

发表评论